The Comprehensive Plan will be drafted in sections. The outline below reflects the current project schedule and the topics the Planning Commission will review along the way. This schedule is subject to change. Check back here for the most up-to-date information as the process moves forward.

Data Collection & Review (June – August 2026 | In Progress)

  • The Planning Commission is reviewing Stillwater Township's existing studies, plans, and data
  • This background work shapes what topics the 2050 plan will focus on

Planning Commission Chapter Reviews (August 2026 – November 2027 )

The Planning Commission will review each chapter of the draft plan on the following schedule:

Task

Timeframe

Develop Public Engagement Plan

June 2026

Data Collection

June - July 2026

Review Vision Statement, Goals, and Policies

July - August 2026

Engagement Event #1: Focused on vision and land use/housing

August 2026 - Annual Picnic

Chapter review: Land Use and Housing

September - October 2026

Chapter review: Wastewater, Water Supply, and Surface Water

November 2026 - January 2027

Chapter review: Climate and Natural Systems

February - April 2027

Engagement Event #2: Focused on parks and transportation

May 2027 - tbd

Chapter review: Parks & Trails and Transportation

May - July 2027

Implementation

July - September 2027

Review and Finalize a Draft

September-November 2027

Engagement Event #3: Focused on the draft implementation

October 2027 - tbd

Agency Review Period

November 2027 - April 2028

Public Hearing

May 2028

Send for Metropolitan Council Review

June 2028

Plan Adoption (November 2027 – June 2028 | Upcoming)

  • Neighboring municipalities review the draft plan
  • Public hearing and formal adoption by the Town Board
  • Plan submitted to and authorized by the Metropolitan Council

The Imagine 2050 Comprehensive Plan must be completed and adopted by December 2028. Check back here for event announcements and ways to get involved.